Scale installation requires road work at Keremeos landfill

Contract for $60,000 awarded to WIldstone Construction for road realignment at the Keremeos landfill

The Regional Board awarded Wildstone Construction and Engineering Ltd. a $60,320 project to install a scale and do some required road realignment at the Keremeos Landfill.

The regional district administers the Keremeos Solid Waste Transfer Site. In 2012 BFI Canada donated a scale to the RDOS for use at the Keremeos landfill. The regional district is now ready to install the scale but will need to realign existing on site roadways to accommodate the device.

Funding for the work will come through capital expenditures for Areas “B” and “G” and Keremeos refuse funds. The project was budgeted for in the 2012 and 2013 budget.