Site C will go ahead, one year later and $5.3 billion more, the NDP announced Feb 26. (BC Hydro image)

Site C will go ahead, one year later and $5.3 billion more, the NDP announced Feb 26. (BC Hydro image)

B.C. to go ahead with Site C dam, with new $16B budget and delayed to 2025

Reviews recommend more oversight, beefed up foundation stability work

Premier John Horgan says his government will continue building the Site C mega dam in northeastern B.C., with an increased budget of $16 billion and a one year delay.

Last August, the government commissioned a special review after BC Hydro acknowledged a serious concern about the dam’s foundational stability. Those reports were made public Friday (Feb. 26), with the province accepting all recommendations.

Special advisor Peter Milburn recommended additional oversight, but did not find evidence of mismanagement.

The government calculated it would cost $10 billion to terminate the dam, and that it will be preferable to complete Site C at the higher price than to absorb the loss. Horgan said cancelling the dam would have an immediate impact to ratepayers of an estimated 26 per cent rate increase over 10 years.

About $6 billion has already been spent, and construction on the dam is over half complete, BC Hydro said.

The Peace River has been diverted, the coffer dams are done and two of the massive turbines have arrived from Brazil. Energy Minister Bruce Ralston also said most of the environmental impacts have already occurred.

In reaction to the announcement, Green Party leader Sonia Furstenau criticized the decision, saying “this isn’t the last time [British Columbians] are going to hear about costs going up.” The Green Party have consistently opposed the dam.

The BC Liberals, who initially approved the dam under former premier Gordon Campbell, have not released an official statement. Interim leader Shirley Bond did re-tweet a comment from pundit Shane Mills saying the NDP “have completely bungled oversight of project of project that was on-time and on-budget.”

RELATED: BC Liberal critic blasts ‘lack of transparency’ on Site C

When the Liberals left power it 2017, they said the project was on time and on budget, but when the BC Utilities Commission reviewed the project later that year, they called that claim into question, predicting probable cost overruns and delays.

The Union of B.C. Indian Chiefs has also consistently opposed the dam on the grounds that the First Nations in the area were not adequately consulted and did not give their consent – impact benefit agreements notwithstanding – despite the province’s voice interest in reconciliation.

Kukpi7 Judy Wilson, UBCIC Secretary-Treasurer, added that the UN Committee on the Elimination of Racial Discrimination has called on Canada to suspend Site C until it has the free, prior and informed consent of Indigenous Peoples.

RELATED: Open letter urges B.C. to pause work at Site C dam to review costs, geotechnical issues

As for geotechnical concerns, engineers virtually evaluated the small movement shifts that had been observed and recommended solutions to shore up the strength of the foundation. These necessary changes plus COVID-19 adjustments make up about half of the increases costs, while the remaining $2.6 billion is set for other unrelated cost overruns.

The actual rate increase from completing the project are unknown, as they will not take effect until the dam is complete – now estimated for 2025. BC Hydro has estimated a roughly $36 annual increase for an average rate payer.

RELATED: First Nation calls for release of Site C report in open letter to premier

The dam has been controversial since the 1980s when it was first proposed as a series of dams on the Peace River. Supporters say the mega dam will supply B.C. with stable energy to meet growing capacity needs.

Those opposed group under a variety of reasons, a primary critique being the ballooning budget.

Site C was originally approved with an $8.8 billion budget in 2014. It increased to $10.7 billion after the BC Utilities Commission reviewed the project in 2017 when the NDP took over government.

Concerns around dam stability have been raised by the public for years. Other complaints are about the ecological impact, First Nations rights in the area, and whether B.C. really needs the power supply.

Do you have something to add to this story or something else we should report on? Email: zoe.ducklow@blackpress.ca


BCHydroenergy sector

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Penticton Christian School. (Facebook)
COVID-19 exposure at Penticton independent school

The exposures are the latest in a quickly growing list in the Interior

Participants are encouraged to light a candle and watch the streamed event from home as speakers honor the lives of those lost to overdose from Gyro Bandshell in Penticton April 14, 2021. (Facebook photo)
Vigil for 5th anniversary of B.C. overdose crisis to be held in Penticton

To honor the lives lost to the overdose crisis and bring a call of action to policymakers

The Regional District of Okanagan-Similkameen will speed up the process for hospitality businesses looking to set up patios during the latest COVID-19 restrictions. Under the most recent restrictions, indoor dining is prohibited, but patio dining is allowed. (John Arendt - Summerland Review)
Regional District of Okanagan-Similkameen speeds up patio permit approval

Initiative to help hospitality businesses affected by latest COVID-19 restrictions

B.C's COVID-19 dashboard shows the peaks and valleys of cases prior to the record daily report of 132 on April 9, 2021. (Dashboard image)
Interior Health has record day of COVID-19 cases

132 cases reported Friday, April 9, more deaths in Vernon hospital outbreak

The Town of Oliver’s Town Offices, which the town wants to get designated a heritage site. (Black Press)
Oliver council to weigh nixing alerts for water leaks

Staff say the policy has served its purpose in fixing the majority of leaks

B.C. Health Minister Adrian Dix and Premier John Horgan describe vaccine rollout at the legislature, March 29, 2021. (B.C. government)
1,262 more COVID-19 infections in B.C. Friday, 9,574 active cases

Province’s mass vaccination reaches one million people

Winter driving conditions returned to the Coquihalla Highway on April 10. (ICBC image)
Coquihalla motorists warned of fresh snow

Five to 10 cm of snow is expected today for the mountain highway.

Tyson Ginter, 7, is proud of his latest Hot Wheels he recently received by Quesnel RCMP Const. Matt Joyce. (Photo submitted)
B.C. Mountie handing out toy cars to light up children’s faces

‘A lot of times it will be the only interaction they have with the police,’ says Const. Matt Joyce

Chief Public Health Officer Theresa Tam speaks during a technical briefing on the COVID pandemic in Canada, Friday, January 15, 2021 in Ottawa. THE CANADIAN PRESS/Adrian Wyld
Canada’s ICUs see near-record of COVID-19 patients last week as variant cases double

Last week, Canadian hospitals treated an average of 2,500 patients with COVID-19, daily, up 7% from the previous week

University of Victoria rowing coach Barney Williams at the University of Victoria in Victoria, B.C. THE CANADIAN PRESS/Chad Hipolito
UVic, women’s rowing coach deny former athlete’s allegation of verbal abuse

Lily Copeland alleges coach Barney Williams would stand close to her and speak aggressively in the sauna

Vernon Secondary School. (Google Maps)
Case of COVID-19 at North Okanagan high school

VSS exposure announced late Friday, April 9

Librarian Katie Burns with the Fraser Valley Regional Libraries poses for a photo in Chilliwack on June 18, 2019. Monday, April 12, 2021 is Library Workers’ Day. (Jenna Hauck/ Chilliwack Progress file)
Unofficial holidays: Here’s what people are celebrating for the week of April 11 to 17

Library Workers Day, That Sucks! Day, and Wear Your Pyjamas to Work Day are all coming up this week

Bart and Tracey Larson enjoying a Begbie Cream Ale. The couple have been together for 40 years. (Liam Harrap - Revelstoke Review)
The art of really good beer: Revelstoke brewery celebrates 25 years

Mt. Begbie Brewery owners Bart and Tracey Larson reflect on their company’s history

The Royal’s 1951 visit to Revelstoke. (Photo by Revelstoke Museum and Archives #17)
PHOTOS: Prince Philip visited Revelstoke – twice

The prince died April 9 at the age of 99

Most Read