The National Energy Board has released a draft list of 145 conditions for approval of Kinder Morgan Canada’s oil pipeline expansion project, including environmental protection plans for land and marine operations.

Conditions include the possibility of dredging for the expansion of the Westridge Marine Terminal in Burnaby, where the original Trans Mountain pipeline has delivered crude oil and refined products since 1953.

Kinder Morgan is proposing to twin the line to ramp up shipments of diluted bitumen from northern Alberta that began intermittently in the late 1980s. The $5.4 billion expansion project would nearly triple the line’s capacity to 890,000 barrels per day, resulting in a seven-fold increase in oil tankers entering and leaving Vancouver harbour.

Kinder Morgan Canada president Ian Anderson said Thursday the company will be seeking clarification on the timing of some of the conditions, and will file its comments to the NEB review panel Aug. 20. Most major conditions, including plans for watercourse crossings along the route, are to be filed at least 90 days before construction begins.

“Our initial review of the draft conditions is that they are rigorous but achievable,” Anderson said.

NEB hearings are to resume Aug. 24, where the B.C. government is expected to formalize its position, based on Premier Christy Clark’s five conditions for new heavy oil pipelines. They include a “world-class” spill response capability on land and sea, approval and benefit sharing by affected First Nations, and a still-undefined “fair share” of benefits for the province.

Those conditions were included in B.C.’s position opposing the Enbridge Northern Gateway project, which the federal government approved with its own list of more than 200 conditions. The province does not have authority to veto either pipeline project, as each would run from Alberta to B.C.

Draft conditions for Trans Mountain include identification of all sites on the proposed second line affected by earthquake, including the “Holocene for Sumas Fault, Vedder Mountain Fault, Fraser River-Straight Creek Fault and Rocky Mountain Trench, as well as other possible hidden faults.”

Conditions also include submitting records of landowner consultation on the route, and a plan for aboriginal participation in monitoring construction.

 

Just Posted

Funding changes mean closure for Success By 6

B.C. making major changes to early childhood development funding

Back to work for Penticton businesses impacted by bomb threats

Multiple car dealerships were evacuated as the result of an international e-mail hoax

Two men arrested in Lower Similkameen on outstanding warrants

RCMP had a busy Sunday making three big arrests related to the Keremeos area

Okanagan College unlocks time capsule

Items placed in 1993 and kept in capsule in library opened at special ceremony

VIDEO: Royals reveal the images on their Christmas cards

Prince William and his wife Kate are shown outside in casual clothes, their three young children in tow

ICBC to apply for 6.3% hike to basic insurance rates

Crown Corporation said it will be submitting its next basic rate application to the British Columbia Utilities Commission Friday

Media, robotics, Indigenous studies coming to B.C. Grade 12 classrooms in 2019-20

Provincial tests are also being changed for students in Grade 10 to 12, the Education Ministry said

Stranded B.C. trucker writes final wishes before being rescued 3 days later

‘I was just praying someone would come along’

Canfor Corp. extending temporary curtailment of sawmills in B.C.; cutting hours

Vancouver-based company says the decision is due to declining lumber prices, high log costs and log supply constraints

Canada’s prospective world junior team members await final roster decisions

Thirty-four players were invited to the national junior selection camp

Avalanche control scheduled tomorrow on Highway 1 east of Revelstoke

Avalanche control work is scheduled along Highway 1 on Dec 15. From… Continue reading

Family searching for B.C. professor last seen at Colombian salsa club

Ramazan Gencay, a professor in economics at Simon Fraser University, was last seen in Medellin

Final phase of Kelowna hospital cardiac centre completed

Finishing new recovery rooms last stage of $381 million project

Most Read