Premier Christy Clark and BC Hydro CEO Jessica McDonald announce main contractor for Site C dam construction at a BC Hydro substation in Burnaby Wednesday.

Contractors picked for Site C construction

Samsung of Korea, ACCIONA of Spain and Petrowest to sign BC Hydro's biggest-ever construction contract for Peace River dam

BC Hydro has selected its main contractor to construct the third dam on the Peace River, and is finalizing a $1.5 billion contract for a dam and river diversion that is the largest in the utility’s history.

The three members of Peace River Hydro Partners are Korean engineering and electronics giant Samsung, Spanish dam and infrastructure specialist ACCIONA and Petrowest Corp., a Calgary-based company that has expanded from oil and gas construction to large infrastructure in northeast B.C. and Alberta.

Petrowest and ACCIONA worked on the recently completed Fort St. John hospital, and ACCIONA has built hydro dams in Spain and Chile. Samsung has built hydro dams, roads, buildings, tunnels, bridges and airports.

Energy Minister Bill Bennett said the contract will be for a fixed price to build the main “civil works,” which include excavation, river diversion tunnels, intake and outlet structures, a kilometre-long earth-filled dam, a 70-metre-high concrete buttress and a road network.

Bennett said work can proceed in winter, and he is confident BC Hydro can stay within its estimated project cost of $8.3 billion.

When the decision to proceed was made a year ago, oil and gas activity was high and there were concerns about labour shortages. But with a continuing slump in oil, natural gas and mineral prices, there are idled workers and equipment in Fort McMurray and other sites in Western Canada.

“Mining is really slow right now and LNG has not yet taken off, so you actually have almost a perfect circumstance for BC Hydro to be entering into its major contracts on Site C,” Bennett said.

Petrowest CEO Rick Quigley said the project will hire locally first, from around B.C. second and elsewhere in Canada third before looking outside the country for skilled labour.

BC Hydro also identified Peace River Hydro Partners’ labour agreements with Christian Labour Association Canada and Construction Maintenance and Allied Workers’ Canada, which broke away from the U.S. international carpenters’ union in 2007.

B.C. Building Trades executive director Tom Sigurdson issued a statement protesting the choice.

“Premier Clark has long said that B.C. workers should be the first in line for Site C work,” Sigurdson said. “This has not been the case so far under the first major contract, awarded to a large Alberta company which has one of four workers on site from out of province.”

 

Just Posted

Okanagan-Shuswap Weather: Most long-weekend rain has already fallen

A mix of sun and cloud is expected for the last two days of the the Victoria Day weekend.

Update: Mother dead, youth in critical condition after carbon monoxide poisoning at Sandy Point Campground

The woman was found unresponsive insider her tent and the youth was taken via air ambulance to hospital

Penticton Indian Band councillor trying for federal seat

Joan Phillip acclaimed as NDP candidate for Central Okanagan-Similkameen-Nicola

Former Greyhound bus drivers gather in the Okanagan for one last hurrah

Bash kicks off Friday in Penticton and runs until Sunday

Some South Okanagan students are $1,000 richer

Million Dollar Bursary Program offers bursaries each year to Interior Savings’ young members

UPDATE: B.C. pilot killed in Honduras plane crash

The crash happened in the Roatan Islands area, according to officials

B.C. VIEWS: Reality of our plastic recycling routine exposed

Turns out dear old China wasn’t doing such a great job

Okanagan tattoo fundraiser draws tons of support

Lineup around the block in Vernon for start of Five Fathoms Tattoo event for Children’s Hospital

Carbon dioxide at highest levels for over 2.5 million years, expert warns of 100 years of disruption

CO2 levels rising rapidly, now higher than at any point in humanity’s history

Fundraising campaign for church shooting victim exceeds goal

A seperate campaign for the man killed in the April 14 shooting is nearing $25,000 raised.

Crews responding to car crash in West Kelowna

A collision has been reported at the intersection of Carrington Road and Butt Road.

Court decision prompts regional district to throw flood mitigation back at province

Public safety minister maintains Newsome Creek concerns in hands of local government

Woodworth purchased Summerland rink, created butcher operation

Giant’s Head Rink had been one of three facilities in Summerland

Get those flowers competition ready

Gardeners will come together June 29, for the 22nd Juried Flower Show

Most Read