The Trans Canada Highway at Salmon Arm is subject to the latest of a long series of widening projects extending to the Alberta border. (B.C. transportation ministry)

B.C. highway widening job reduced, costs still up $61 million

Union-only project scales back work to widen Trans-Canada

The B.C. NDP government’s union-restricted road construction program is sparking new questions about a steep increase in costs, even as a section of Trans-Canada Highway widening work has been significantly scaled back.

Widening the Trans Canada Highway east of Kamloops is one of three major projects the NDP government designated for what it describes as “community benefits agreements.” They restrict the workforce to 19 mostly U.S.-based construction trade unions under a 336-page agreement with a new Crown corporation created to administer it. The others are replacement of the Pattullo Bridge at Surrey, and the Broadway subway extension in Vancouver.

The latest contract to be let under the agreement is for a section of Highway 1 at Salmon Arm, announced in June at a budget of $185 million, including $31 million from Ottawa. The announcement by Transportation Minister Claire Trevena explained the reduced size, three-year delay and $61 million increase in costs was because the 2016 project was completed without sufficient engineering and local engagement work.

Kamloops-South Thompson MLA Todd Stone, the former B.C. Liberal transportation minister, said the work was done by 2017, including consulting the Neskonlith Band. Questioned on the project by Stone and Shuswap MLA Greg Kyllo, Trevena said there is still no agreement with Neskonlith to proceed with a large portion of the widening.

Stone said the 9.9 km project has been reduced to 4.9 km, “with a two-lane section stuck in the middle between Hoffman’s Bluff and Chase West,” and elimination of an underpass.

“These massive cost overruns and project scope reductions are the direct result of the NDP delaying these projects for upwards of three years, on top of additional costs in the millions of dollars resulting from the NDP’s imposition of community benefit agreements requiring projects to utilize labour of one of 19 NDP approved unions,” Stone told Black Press July 6.

Trevena said agreement with Neskonlith is needed for the federal share of the money to be provided, and other costs were affected by a “hot market” for construction, up until the COVID-19 pandemic had broad effects on the economy.

“I think what we have now is the realistic budget,” Trevena said.

A tight construction labour market and high prices for steel and asphalt were also cited in the 35-per cent jump in cost for the first contract awarded under the union agreement, east of Revelstoke.

Trevena noted the first Salmon Arm contract went to a Kamloops-based company, and said the new union structure ensures more local, female and Indigenous people being hired as apprentices. That claim has been a source of bitter dispute with newer unions and non-union construction companies, who say they employ 85 per cent of people currently working in construction trades.

Premier John Horgan and the B.C. and Yukon Building Trades say it’s the completion of apprenticeships that is most important, and traditional building trades have an edge there.

RELATED: Contractors picked for Pattullo Bridge replacement

RELATED: Cost jumps 35% for Revelstoke widening section

The new Crown corporation, B.C. Infrastructure Benefits, controls payroll, union dues and benefits for designated public projects. It diverts an additional 25 cents per hour worked to a new union organization called the Allied Infrastructure and Related Construction Council of B.C., and another seven cents per hour to building trades union funds for health and safety.

Non-union or independent union-affiliated companies can still bid on projects, but their employees are required to join one of the designated international unions within 30 days of starting work.

When the $1.38 billion contract to build a new Pattullo Bridge was awarded in January, Trevena acknowledged that the union-only deal would add about seven per cent to the cost. The 83-year-old four-lane bridge is being replaced with another four-lane bridge with added pedestrian and bicycle lanes, and a new off-ramp to Highway 17, the South Fraser Perimeter Road.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Missing toddler found safe near Beaverdell

The child had been missing in the Clark Lake area for more than two hours

Penticton mail carriers ask dog owners to keep pets secured

Loose dogs have put mail carriers in danger and made physical distancing difficult

Morning Start: Women can give birth after they die

Your morning start for Wednesday, Aug. 12, 2020

COVID-19 outbreak at Oliver farm declared over

There continues to be other community exposure events in the Interior Health region

Morning Start: The Exorcist film set was haunted

Your morning start for Tuesday, Aug. 11, 2020

B.C. records new COVID-19 death, 85 more cases; Horgan calls on celebrity help

This brings the total number of active confirmed cases to 531 across the province

Horvat scores 2 as Vancouver Canucks beat Blues 5-2 in NHL playoff opener

Game 2 in best-of-seven series goes Friday night

Federal Conservative leadership candidate skirts COVID-19 rules at Kelowna rally

Derek Sloan held a rally in Kelowna that had more than 50 people, which is against health orders from the province

Teachers to get 2 extra days to prepare for students’ return, now set for Sept. 10

Students will first start with orientation and learn rules of COVID-19 classroom policies

High-volume littering at Cape Scott draws ire from hiking groups

Popular Vancouver Island hiking spot not closing, but frustration about crowding grows

SFU to drop ‘Clan’ varsity team name

The ‘Clan’ name is shortened from ‘Clansmen,’ and was introduced roughly 55 years ago

New Tory leader must build a strong team in Commons and for the campaign: Scheer

Scheer marked his final day in the House of Commons today as leader of the Opposition

South Okanagan restaurant ranked among world’s best by TripAdvisor

The Hooded Merganser was ranked within the top 10 per cent of all restaurants by TripAdvisor reviews

Highway 97 upgrade option for Peachland faces 20-year delay

Peachland council disappointed by highways department decision

Most Read